Infrastructure funding briefing

NSW’s infrastructure funding leak just sprang another hole

Moving local contributions from Construction Certificate to Occupation Certificate sounds like a timing tweak. Made permanent, it leaves NSW councils around $850 million short, and that cash never comes back.

≈ $850mstatewide permanent cash shortfall (central; range $600m–$1.2bn)
≈ $125mCity of Sydney (indicative)
2–3 yearstypical CC-to-OC lag for an apartment building
≈ 2/3share of the impact on CBD and middle-ring infill councils

Why it matters

Councils are owed the same amount, but permanently hold less cash

Moving payment from CC to OC doesn’t change what developers pay. It changes when they pay. A temporary deferral catches up when it ends. A permanent one doesn’t, so councils stay that far behind for good.

Greenfield councils are largely unaffected, because subdivision pays before the subdivision certificate. Infill councils, where apartments pay at CC, carry most of the impact.

Chart: a temporary deferral causes a cash gap followed by a catch-up when it ends; a permanent deferral causes the same gap but no catch-up
Chart: City of Sydney contributions receipts fell from $41m in 2019–20 to $21m in 2020–21 during the COVID deferral, then rose to $74m in 2022–23 when it ended

The evidence

The COVID deferral shows the pattern

City of Sydney’s contributions receipts fell from about $41 million in 2019–20 to $21 million in 2020–21 while payment was deferred to OC. They spiked to $74 million in 2022–23 when the deferral ended.

That catch-up only happened because the deferral was temporary.

NSW local infrastructure contributions

What does moving contributions from CC to OC cost your council?

Estimator

What would it cost your council?

The NSW Government has committed to permanently deferring payment of local infrastructure contributions from the Construction Certificate to the Occupation Certificate. Enter your council type and annual receipts for an indicative estimate.

$million
Use an average of recent years from your financial statements (the note on developer contributions). Exclude s7.4 planning agreements and works in kind. The $20m shown is an example.
Scenario
Adjust assumptions
Share paid at CC: the proportion of receipts that currently comes from consents requiring payment before the CC. Subdivision (paid before the subdivision certificate) and complying development are not affected.
Permanent cash shortfall–

Receipts fall by–
Ongoing cost of funds–
Equivalent to–of annual receipts

Annual receipts with a permanent deferral

Deferral applies to new consents from the start of Year 1. Receipts return to normal, but the shaded amount is never received early again.

ReceiptsDeferred (the cash gap)

Range for this council type

ScenarioShare at CCLagCash shortfallCost of funds a year

How the estimate works

Cash shortfall = annual receipts × share paid at CC × CC-to-OC lag.

Each affected development still pays in full, but two to three years later. Under a temporary deferral, as during COVID, the dip is followed by a catch-up when payment timing reverts. Under a permanent change there is no catch-up, so the council stays that far behind for good.

Statewide, InfraGrowth estimates a shortfall of about $850 million (range $600 million to $1.2 billion), based on the financial statements of around 40 NSW councils.

Limits

  • Indicative only. Defaults are typical values for each council type, not figures for any particular council.
  • Assumes the change applies to new consents. If existing consents are brought in, the dip arrives sooner and deeper.
  • Does not model growth in receipts, indexation, or the risk of payments being missed at OC.
  • Not financial advice. A council-specific estimate needs your development pipeline and consent conditions.

Need a figure you can take to your executive?

InfraGrowth Planning prepares council-specific assessments by development pathway and transition scenario, using your consent and pipeline data.

Jonathon Carle, Founder and Directorjonathon@infragrowth.com.auwww.infragrowth.com.au

InfraGrowth Planning Pty Ltd · ABN 85 691 199 596 · Sydney NSW

InfraGrowth Planning acknowledges the Traditional Custodians of the lands on which we live and work, and pays respect to Elders past and present.

Includes your inputs, the results and the method notes.

The fix

Keep the timing change without the cash hole

  • A State bridging facility through TCorp: pay councils at CC and collect from developers at OC.
  • Count contributions in the debt service cover ratio, or set a sunset on the change.
  • Verify payment before any OC, including interim and phased OCs, with security allowed.
  • Publish council-by-council impacts before commencement.

About the author

Jonathon Carle

Jonathon Carle

Jonathon is the founder and director of InfraGrowth Planning. He has more than 25 years’ experience in infrastructure planning and funding across local government, the NSW Government and consulting.

jonathon@infragrowth.com.au

Related briefing

NSW’s billion-dollar infrastructure funding leak

The unindexed s7.11 thresholds have suppressed an estimated $730 million in contributions capacity since 2010. That is lost value; the CC-to-OC shortfall is a permanent timing gap, so the two are not added together.

Read the thresholds briefing →

Important qualifications

This is a modelled estimate, not an audited loss. It is based on s7.11 and s7.12 cash receipts from the audited financial statements of about 40 councils (about 87% of statewide receipts), with the remainder estimated.

It assumes the change applies to new consents. Bringing in existing consents would bring the dip forward.

It should not be added to the $730 million threshold estimate: one is lost value, the other a permanent timing gap.

Method

How the estimate was built

01  Formula

Permanent cash shortfall = annual contributions receipts × share currently paid at CC × typical CC-to-OC lag (years)

Ongoing cost = shortfall × council cost of funds (5% assumed)

02  Data

  • s7.11 and s7.12 cash receipts compiled from the audited financial statements of 40 NSW councils (latest two years averaged), covering about 87% of statewide receipts (about $666 million of an estimated $766 million a year).
  • Remaining councils estimated by council type (about $100 million).
  • Excludes s7.4 planning agreements and works in kind.
  • Councils compiled by type: CBD 3, middle-ring infill 15, regional city 10, mixed growth 6, greenfield 4, rural 2.

03  Assumptions by council type

Council typeShare paid at CC
low / central / high
CC-to-OC lag (years)
low / central / high
CBD or major centre85 / 90 / 95%2.5 / 2.75 / 3.5
Middle-ring infill80 / 85 / 90%1.5 / 2.0 / 2.5
Regional city40 / 50 / 60%1.5 / 1.7 / 2.0
Mixed growth20 / 30 / 40%1.5 / 2.0 / 2.5
Greenfield5 / 10 / 15%1.0 / 1.2 / 1.5
Rural or regional town30 / 40 / 50%1.0 / 1.0 / 1.0

04  Results by council type (central case, $ million, rounded)

Council typeAnnual receiptsCash shortfall
CBD or major centre≈ 85≈ 207
Middle-ring infill≈ 220≈ 373
Regional city≈ 135≈ 116
Mixed growth≈ 225≈ 134
Greenfield≈ 65≈ 8
Rural or regional town≈ 30≈ 13
NSW total≈ 766≈ 850
range ≈ 600 to ≈ 1,190

Figures rounded; may not sum.

05  Note

Estimates are indicative and by council type. Individual council results depend on development mix, consent conditions and transition arrangements. Council-specific assessments are available on request.